Energy Projects Near You

Ballynagilly Renewable Energy Project (18.4 MW wind farm)

Ballynagilly Renewable Energy Project is an 18.4 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 26 March 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
appeal withdrawnstatus in REPD
26 March 2019record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
26 June 2015Application submitted
11 May 2018Refused by the planning authority
7 September 2018Appeal lodged
6 February 2019Appeal withdrawn

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
appeal withdrawn
Record last updated
26 March 2019
Operator or applicant
Island Renewable Energy
Planning authority
Mid Ulster
Planning application reference
LA09/2015/0459/F
Appeal reference
2018/A0083
Turbines
8
Turbine height
127 m
Address (REPD)
Stanley Bell and Sons Ltd Quar, Ballynagilly Townland, Lissan, Cookstown, Co Tyrone
Council area (by location)
Mid Ulster
Time to decision
150 weeks
REPD reference
5474

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beltonanean Wind Farmwind farm12appeal withdrawn4.6
Crockandunwind farm15operational5.8
Battery Energy Storage System Development in Moneymorebattery storage20approved, not built8.4
Cullion wind farmwind farm25application submitted8.8
Mullaghturk Mountainwind farm10.5refused9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6916, -6.807).