Ballynagilly Renewable Energy Project (18.4 MW wind farm)
Ballynagilly Renewable Energy Project is an 18.4 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 26 March 2019.
18.4 MWwind farm
appeal withdrawnstatus in REPD
26 March 2019record last updated
Mid Ulstercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 June 2015 | Application submitted |
| 11 May 2018 | Refused by the planning authority |
| 7 September 2018 | Appeal lodged |
| 6 February 2019 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 18.4 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 26 March 2019
- Operator or applicant
- Island Renewable Energy
- Planning authority
- Mid Ulster
- Planning application reference
- LA09/2015/0459/F
- Appeal reference
- 2018/A0083
- Turbines
- 8
- Turbine height
- 127 m
- Address (REPD)
- Stanley Bell and Sons Ltd Quar, Ballynagilly Townland, Lissan, Cookstown, Co Tyrone
- Council area (by location)
- Mid Ulster
- Time to decision
- 150 weeks
- REPD reference
- 5474
Who decides
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Beltonanean Wind Farm | wind farm | 12 | appeal withdrawn | 4.6 |
| Crockandun | wind farm | 15 | operational | 5.8 |
| Battery Energy Storage System Development in Moneymore | battery storage | 20 | approved, not built | 8.4 |
| Cullion wind farm | wind farm | 25 | application submitted | 8.8 |
| Mullaghturk Mountain | wind farm | 10.5 | refused | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6916, -6.807).