Energy Projects Near You

Beltonanean Wind Farm (12 MW)

Beltonanean Wind Farm is a 12 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 30 August 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
appeal withdrawnstatus in REPD
30 August 2018record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
19 January 2015Application submitted
24 November 2017Refused by the planning authority
22 March 2018Appeal lodged
20 August 2018Appeal withdrawn

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
appeal withdrawn
Record last updated
30 August 2018
Operator or applicant
Island Renewable Energy
Planning authority
Mid Ulster
Planning application reference
I/2014/0413/F
Appeal reference
2017/A0257
Turbines
6
Turbine height
127 m
Address (REPD)
Beltonanean Ballynasollus, Ballynasollus, Beleevna-More and Ballynagill, Cookstown,
Council area (by location)
Mid Ulster
Time to decision
149 weeks
REPD reference
4998

Earlier applications for this site

ApplicationMWSubmittedOutcome
Beltonanean Wind Turbine I/2010/0211/F2.317 May 2010replaced by a revised application

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ballynagilly Renewable Energy Projectwind farm18.4appeal withdrawn4.6
Mullaghturk Mountainwind farm10.5refused5.1
Crockandunwind farm15operational8.8
Cregganconroewind farm13.8operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.69, -6.8785).