Beltonanean Wind Farm (12 MW)
Beltonanean Wind Farm is a 12 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 30 August 2018.
12 MWwind farm
appeal withdrawnstatus in REPD
30 August 2018record last updated
Mid Ulstercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 19 January 2015 | Application submitted |
| 24 November 2017 | Refused by the planning authority |
| 22 March 2018 | Appeal lodged |
| 20 August 2018 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 30 August 2018
- Operator or applicant
- Island Renewable Energy
- Planning authority
- Mid Ulster
- Planning application reference
- I/2014/0413/F
- Appeal reference
- 2017/A0257
- Turbines
- 6
- Turbine height
- 127 m
- Address (REPD)
- Beltonanean Ballynasollus, Ballynasollus, Beleevna-More and Ballynagill, Cookstown,
- Council area (by location)
- Mid Ulster
- Time to decision
- 149 weeks
- REPD reference
- 4998
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Beltonanean Wind Turbine I/2010/0211/F | 2.3 | 17 May 2010 | replaced by a revised application |
Who decides
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Ballynagilly Renewable Energy Project | wind farm | 18.4 | appeal withdrawn | 4.6 |
| Mullaghturk Mountain | wind farm | 10.5 | refused | 5.1 |
| Crockandun | wind farm | 15 | operational | 8.8 |
| Cregganconroe | wind farm | 13.8 | operational | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.69, -6.8785).