Solar, wind and battery projects near Cookstown (BT80)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT80 (Mid Ulster): 3 are waiting for a planning decision, 5 approved but not yet running, 1 operational. The largest live scheme is Battery Energy Storage System Development in Moneymore (20 MW battery storage, approved on 11 December 2025, not yet built), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BT80
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dale Farmsolar farm | solar farm | 4.9 | operationalupdated Aug 2018 | Sep 2015 | granted Jan 2016 | Aug 2018 | Mid Ulster | 0.9 |
| Battery Energy Storage System Development in Moneymorebattery storage | battery storage | 20 | approved, not builtupdated Jan 2026 | Dec 2024 | granted Dec 2025 | Jan 2026 | Mid Ulster | 4.2 |
| Doraville Wind Farmwind farm | wind farm | 119 | refusedupdated Jan 2021 | Jul 2015 | refused Oct 2020 | Jan 2021 | Mid Ulster | 5.2 |
| Ballynagilly Renewable Energy Projectwind farm | wind farm | 18.4 | appeal withdrawnupdated Mar 2019 | Jun 2015 | refused May 2018 | Mar 2019 | Mid Ulster | 6.4 |
| Dirnan Road Wind Turbinewind turbine | wind turbine | 3 | refused on appealupdated Aug 2016 | Jul 2014 | refused Jun 2015 | Aug 2016 | Mid Ulster | 6.9 |
| Drum Road, Cookstown Solar & Battery Developmentsolar farm | solar farm | 1 | application submitted may be out of dateupdated Jun 2023 | Mar 2023 | — | Jun 2023 | Mid Ulster | 7.8 |
| Beltonanean Wind Farmwind farm | wind farm | 12 | appeal withdrawnupdated Aug 2018 | Jan 2015 | refused Nov 2017 | Aug 2018 | Mid Ulster | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sessiagh Roadwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2022 | Oct 2020 | granted Apr 2022 | Jan 2022 | Mid Ulster | 4.7 |
| Gortagammon Road Replacement Turbinewind turbine | wind turbine | 0.2 | approved, not builtupdated Jun 2024 | Feb 2021 | granted May 2024 | Jun 2024 | Mid Ulster | 6.3 |
| Wind Turbine Development in Moneymorewind turbine | wind turbine | 0.2 | application submittedupdated Apr 2025 | Feb 2025 | — | Apr 2025 | Mid Ulster | 6.4 |
| Rockdale Roadwind turbine | wind turbine | 0.3 | application withdrawnupdated Mar 2020 | Feb 2020 | — | Mar 2020 | Mid Ulster | 7.8 |
| Drum Road, Cookstown Solar & Battery Developmentbattery storage | battery storage | — | application submitted may be out of dateupdated Jun 2023 | Mar 2023 | — | Jun 2023 | Mid Ulster | 7.8 |
| Wind Turbine Development in Stewartstownwind turbine | wind turbine | 0.7 | approved, not builtupdated Mar 2024 | Feb 2023 | granted Feb 2024 | Mar 2024 | Mid Ulster | 8.1 |
| Wind Turbine Development in Stewartstownwind turbine | wind turbine | 0.1 | approved, not builtupdated Feb 2022 | Nov 2021 | granted Apr 2022 | Feb 2022 | Mid Ulster | 9.2 |
Distance from the average position of the BT80 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 1 | 0 | 1 | 0 | 1 |
| Wind farm | 3 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 7 | 1 | 4 | 0 | 1 | 1.5 |
| Battery storage | 2 | 1 | 1 | 0 | 0 | 20 |
MW in pipeline: pending, approved and under-construction capacity.
How Mid Ulster decides solar, wind and battery applications
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT80, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.