Energy Projects Near You

Solar, wind and battery projects near Dungannon (BT70)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT70 (Mid Ulster): 2 are waiting for a planning decision, 7 approved but not yet running, 5 operational. The largest live scheme is Derrymeen Battery Energy Storage System (100 MW battery storage, under construction since 1 May 2026), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
2awaiting a decision
7approved, not running
5operational

Projects within 10 km of BT70

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cappaghwind farmwind farm9application withdrawnupdated Apr 2011Apr 2008—Apr 2011Mid Ulster4.2
Eshmorewind farmwind farm6.9operationalupdated Jan 2017Oct 2006granted Oct 2011Jan 2017Mid Ulster5.4
Eshmore Wind Farm Extensionwind turbinewind turbine2.3permission expiredupdated Jul 2019Jul 2015granted Jul 2016Jul 2019Mid Ulster7.0
Derrymeen Battery Energy Storage Systembattery storagebattery storage100under constructionupdated Jun 2026Apr 2024granted Jun 2025Jun 2026Mid Ulster7.6
Battery Energy Storage System in Newmillsbattery storagebattery storage24approved, not builtupdated Aug 2025Apr 2024granted Jul 2025Aug 2025Mid Ulster7.6
Cloghfin Roadwind farmwind farm4.8approved, not built may be out of dateupdated May 2020Jun 2018granted Apr 2019May 2020Mid Ulster8.0
Altmore Roadsolar farmsolar farm4.9abandonedupdated Dec 2017Nov 2015granted May 2016Dec 2017Mid Ulster8.2
Crockagarron Extwind turbinewind turbine2.5operationalupdated Dec 2012Mar 2009granted Dec 2010Dec 2012Fermanagh and Omagh8.9
Gortfinbarwind farmwind farm15operationalupdated Jan 2017Apr 2006granted May 2009Jan 2017Fermanagh and Omagh9.2
Crockagarranwind farmwind farm15operationalupdated Nov 2011Jul 2005granted Jun 2007Nov 2011Fermanagh and Omagh9.3
Inishativewind farmwind farm13.8operationalupdated Jul 2017Nov 2006granted Nov 2010Jul 2017Fermanagh and Omagh9.9
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar PV Array Development in Dungannonrooftop solarrooftop solar0.1approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Mid Ulster5.5
Legilly Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Apr 2020Oct 2019granted Apr 2020Apr 2020Mid Ulster5.5
Tullyaran Roadwind turbinewind turbine0.2approved, not built may be out of dateupdated Sep 2019Feb 2019granted Sep 2019Sep 2019Mid Ulster6.3
Solar Array Development in Dungannonsolar farmsolar farm0.3approved, not builtupdated Jan 2025May 2024granted Dec 2024Jan 2025Mid Ulster7.6
Wind Turbine Development in Dungannonwind turbinewind turbine—application submittedupdated Feb 2025Jan 2025—Feb 2025Mid Ulster7.7
Wind Turbine Development in Dungannonwind turbinewind turbine—application submittedupdated Nov 2024Sep 2024—Nov 2024Mid Ulster8.4
Rockdale Roadwind turbinewind turbine0.3application withdrawnupdated Mar 2020Feb 2020—Mar 2020Mid Ulster9.5

Distance from the average position of the BT70 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201000.3
Rooftop solar101000.1
Wind farm601404.8
Wind turbine722100.5
Battery storage20200124

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT70, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.