Energy Projects Near You

Gortfinbar (15 MW wind farm)

Gortfinbar is a 15 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 December 2016; the record was last updated on 4 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
4 January 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
3 April 2006Application submitted
7 May 2009Planning permission granted
1 September 2015Construction started
22 December 2016Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
4 January 2017
Operator or applicant
Energia Renewables
Planning authority
Fermanagh and Omagh
Planning application reference
K/2006/1089/F
Turbines
6
Address (REPD)
Sixmilecross/Carrickmore, Omagh
Council area (by location)
Fermanagh and Omagh
Time to decision
161 weeks
REPD reference
3933

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crockagarranwind farm15operational0.7
Crockbaravally Wind Farmwind farm7.5operational2.1
Inishativewind farm13.8operational2.6
Crockdunwind farm12.5operational3.4
Eshmorewind farm6.9operational5.0
Altamuskinwind farm7.1operational5.4
Cappaghwind farm9application withdrawn6.0
Slieve Divena Phase 1 Wind Farmwind farm30operational6.8
Slieve Divena Phase 2 Wind Farmwind farm18.8operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.544, -7.0197).