Inishative (13.8 MW wind farm)

Inishative is a 13.8 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 March 2017; the record was last updated on 3 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
3 July 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
10 November 2006Application submitted
12 November 2010Planning permission granted
17 February 2015Construction started
13 March 2017Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
3 July 2017
Operator or applicant
Gaelectric Developments/ CGN Europe Energy
Planning authority
Fermanagh and Omagh
Planning application reference
K/2006/1793/F
Turbines
6
Address (REPD)
Inishative Road, Sixmilecross, Omagh (Slievebeg. Land between Ballygawley and Pomeroy, approximately 1.5km north of Altmore Forest, Townland of Inishative)
Council area (by location)
Fermanagh and Omagh
Time to decision
209 weeks
REPD reference
4245

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crockagarranwind farm15operational1.9
Crockdunwind farm12.5operational2.6
Gortfinbarwind farm15operational2.6
Crockbaravally Wind Farmwind farm7.5operational2.9
Eshmorewind farm6.9operational4.7
Battery Energy Storage System Facility Development in Pomeroybattery storage48approved, not built4.9
Cappaghwind farm9application withdrawn5.9
Cregganconroewind farm13.8operational6.5
Altamuskinwind farm7.1operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5669, -7.0096).