Battery Energy Storage System Facility Development in Pomeroy (48 MW)

Battery Energy Storage System Facility Development in Pomeroy is a 48 MW battery storage project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 June 2026, not yet built; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWbattery storage
approved, not builtstatus in REPD
13 July 2026record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
25 February 2025Application submitted
17 June 2026Planning permission granted
17 June 2031Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
13 July 2026
Operator or applicant
Green Frog Power (Tremoge) Limited
Planning authority
Mid Ulster
Planning application reference
LA10/2025/0207/F
Address (REPD)
Lands Approximately 120m S.W. of Tremoge SubStn. &, Approximately 73m Nw/o Tremoge, Pomeroy
Council area (by location)
Fermanagh and Omagh
Time to decision
68 weeks
REPD reference
18550

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cregganconroewind farm13.8operational2.2
Inishativewind farm13.8operational4.9
Eshmorewind farm6.9operational6.2
Crockdunwind farm12.5operational6.5
Crockagarranwind farm15operational6.7
Cappaghwind farm9application withdrawn7.2
Gortfinbarwind farm15operational7.4
Mullaghturk Mountainwind farm10.5refused7.5
Crockbaravally Wind Farmwind farm7.5operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.604, -6.969).