Crockdun (12.5 MW wind farm)

Crockdun is a 12.5 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 July 2017; the record was last updated on 30 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
operationalstatus in REPD
30 August 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
20 January 2006Application submitted
13 September 2010Planning permission granted
14 July 2016Construction started
14 July 2017Operational

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
operational
Record last updated
30 August 2017
Operator or applicant
ESB (Northern Wind Power)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2006/0074/F
Turbines
5
Address (REPD)
214 Loughmacrory Road, Crockdun, Sixmilecross, Omagh, Co. Tyrone.
Council area (by location)
Fermanagh and Omagh
Time to decision
242 weeks
REPD reference
4320

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crockbaravally Wind Farmwind farm7.5operational1.8
Inishativewind farm13.8operational2.6
Crockagarranwind farm15operational3.0
Gortfinbarwind farm15operational3.4
Altamuskinwind farm7.1operational6.0
Battery Energy Storage System Facility Development in Pomeroybattery storage48approved, not built6.5
Eshmorewind farm6.9operational7.2
Altamuskin Extensionwind farm7.1operational7.4
Cregganconroewind farm13.8operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5689, -7.0494).