Altamuskin Extension (7.1 MW wind farm)

Altamuskin Extension is a 7.1 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 4 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.1 MWwind farm
operationalstatus in REPD
4 May 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
13 April 2011Application submitted
28 January 2015Planning permission granted
1 March 2016Construction started
15 March 2017Operational

Project details

Technology
wind farm
Capacity
7.1 MW
Status (REPD)
operational
Record last updated
4 May 2017
Operator or applicant
Altamuskin Windfarm (Energia)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2011/0239/F
Turbines
3
Turbine height
110 m
Address (REPD)
Sixmilecross, Clogher, Co. Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
198 weeks
REPD reference
4557

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Divena Phase 2 Wind Farmwind farm18.8operational0.6
Slieve Divena Phase 1 Wind Farmwind farm30operational0.6
Altamuskinwind farm7.1operational1.5
Shantavy Scotchwind farm14approved, not built2.9
Classic Marble Showers, Omagh Roadbattery storage73approved, not built2.9
Omagh Road, Garvaghybattery storage50approved, not built3.5
Shantavny Scotchwind farm16.1operational4.2
Crockbaravally Wind Farmwind farm7.5operational6.1
Gortfinbarwind farm15operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5128, -7.1113).