Shantavny Scotch (16.1 MW wind farm)

Shantavny Scotch is a 16.1 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 March 2017; the record was last updated on 19 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.1 MWwind farm
operationalstatus in REPD
19 December 2017record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
29 October 2007Application submitted
24 February 2012Planning permission granted
1 August 2016Construction started
16 March 2017Operational

Project details

Technology
wind farm
Capacity
16.1 MW
Status (REPD)
operational
Record last updated
19 December 2017
Operator or applicant
Tyrone Wind Energy Ltd
Planning authority
Mid Ulster
Planning application reference
M/2007/1407/F
Turbines
7
Address (REPD)
Omagh Road, Ballygawley Co. Tyrone
Council area (by location)
Mid Ulster
Time to decision
226 weeks
REPD reference
4325

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shantavy Scotchwind farm14approved, not built1.4
Omagh Road, Garvaghybattery storage50approved, not built1.4
Classic Marble Showers, Omagh Roadbattery storage73approved, not built2.2
Slieve Divena Phase 2 Wind Farmwind farm18.8operational3.7
Slieve Divena Phase 1 Wind Farmwind farm30operational3.7
Altamuskin Extensionwind farm7.1operational4.2
Slieve Beaghwind farm30application withdrawn5.1
Altamuskinwind farm7.1operational5.1
Gortfinbarwind farm15operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4766, -7.09).