Altamuskin (7.1 MW wind farm)

Altamuskin is a 7.1 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 4 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.1 MWwind farm
operationalstatus in REPD
4 May 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
3 February 2006Application submitted
2 December 2008Planning permission granted
1 March 2016Construction started
15 March 2017Operational

Project details

Technology
wind farm
Capacity
7.1 MW
Status (REPD)
operational
Record last updated
4 May 2017
Operator or applicant
Altamuskin Windfarm (Energia)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2006/0164/F
Turbines
3
Turbine height
110 m
Address (REPD)
Altamooskan (Altamuskin) TD, Sixmilecross, Omagh, Co. Tyrone.
Council area (by location)
Fermanagh and Omagh
Time to decision
148 weeks
REPD reference
4139

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Altamuskin Extensionwind farm7.1operational1.5
Slieve Divena Phase 1 Wind Farmwind farm30operational1.7
Slieve Divena Phase 2 Wind Farmwind farm18.8operational1.7
Shantavy Scotchwind farm14approved, not built3.7
Classic Marble Showers, Omagh Roadbattery storage73approved, not built4.2
Crockbaravally Wind Farmwind farm7.5operational4.6
Omagh Road, Garvaghybattery storage50approved, not built4.6
Shantavny Scotchwind farm16.1operational5.1
Gortfinbarwind farm15operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5222, -7.0946).