Slieve Divena Phase 2 Wind Farm (18.8 MW)

Slieve Divena Phase 2 Wind Farm is an 18.8 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 February 2017; the record was last updated on 27 November 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.8 MWwind farm
operationalstatus in REPD
27 November 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
13 September 2005Application submitted
6 June 2007Planning permission granted
30 May 2016Construction started
16 February 2017Operational

Project details

Technology
wind farm
Capacity
18.8 MW
Status (REPD)
operational
Record last updated
27 November 2017
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2005/1691/F
Turbines
8
Address (REPD)
Slieve Divena Wind Farm Phase II in the townlands of Altcloghfin, Altamuskin and Shantavny Irish, Co Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
90 weeks
REPD reference
4054

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slieve Divena Phase 1 Wind Farmwind farm30operational<0.1
Altamuskin Extensionwind farm7.1operational0.6
Altamuskinwind farm7.1operational1.7
Shantavy Scotchwind farm14approved, not built2.3
Classic Marble Showers, Omagh Roadbattery storage73approved, not built2.5
Omagh Road, Garvaghybattery storage50approved, not built3.0
Shantavny Scotchwind farm16.1operational3.7
Crockbaravally Wind Farmwind farm7.5operational6.2
Gortfinbarwind farm15operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5086, -7.1064).