Energy Projects Near You

Solar, wind and battery projects near Clogher (BT76)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT76 (Mid Ulster): 1 is waiting for a planning decision, 4 approved but not yet running, 4 operational. The largest live scheme is Classic Marble Showers, Omagh Road (73 MW battery storage, approved on 19 June 2026, not yet built), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
1awaiting a decision
4approved, not running
4operational

Projects within 10 km of BT76

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lendrum's Bridge Wind Farmwind farmwind farm5.9operationalupdated Feb 2010Sep 1997granted May 1998Feb 2010Mid Ulster3.1
Lendrum's Bridge Wind Farm ( Extension 2)wind farmwind farm7.3operationalupdated Jan 2004Sep 1997granted May 1998Jan 2004Mid Ulster4.0
Slatbegwind farmwind farm20.7refusedupdated Apr 2012Dec 2006refused Feb 2009Apr 2012Mid Ulster5.4
Slieve Beaghwind farmwind farm30application withdrawnupdated Oct 2013——Oct 2013Mid Ulster5.6
Omagh Road, Garvaghybattery storagebattery storage50approved, not builtupdated May 2026Nov 2024granted Apr 2026May 2026Mid Ulster8.7
Classic Marble Showers, Omagh Roadbattery storagebattery storage73approved, not builtupdated Jul 2026Jul 2024granted Jun 2026Jul 2026Fermanagh and Omagh8.9
Shantavny Scotchwind farmwind farm16.1operationalupdated Dec 2017Oct 2007granted Feb 2012Dec 2017Mid Ulster9.1
Shantavy Scotchwind farmwind farm14approved, not builtupdated Sep 2023Jul 2020granted Dec 2021Sep 2023Mid Ulster9.9
Hunter's Hillwind farmwind farm20operationalupdated May 2016Feb 2005granted Dec 2008May 2016Fermanagh and Omagh9.9
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Omagh Roadwind turbinewind turbine0.5approved, not built may be out of dateupdated Feb 2021Oct 2019granted Feb 2021Feb 2021Mid Ulster8.6
Gort Energy Storagebattery storagebattery storage—application submitted may be out of dateupdated Jun 2020Feb 2020—Jun 2020Fermanagh and Omagh8.9

Distance from the average position of the BT76 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm7014114
Wind turbine101000.5
Battery storage31200123

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT76, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.