Solar, wind and battery projects near Aughnacloy (BT69)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT69 (Mid Ulster): 2 are waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Kilsannagh Lane (0.3 MW wind turbine, approved on 30 April 2020, not yet built; REPD status may be out of date), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
2awaiting a decision
1approved, not running
0operational

Projects within 10 km of BT69

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mullynaveaghwind farmwind farm4.6abandonedupdated Feb 2016Dec 2008granted Dec 2010Feb 2016Mid Ulster8.2
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kilsannagh Lanewind turbinewind turbine0.3approved, not built may be out of dateupdated Apr 2020Oct 2019granted Apr 2020Apr 2020Mid Ulster8.3
Tannaghlane Road, Caledonwind turbinewind turbine—application submitted may be out of dateupdated Mar 2026Oct 2023—Mar 2026Mid Ulster8.6
Wind Turbine Development in Dungannonwind turbinewind turbine—application submittedupdated Nov 2024Sep 2024—Nov 2024Mid Ulster9.8

Distance from the average position of the BT69 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100000
Wind turbine321000.3

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT69, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.