Solar, wind and battery projects near Dungannon (BT71)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT71 (Mid Ulster): 3 are waiting for a planning decision, 10 approved but not yet running. The largest live scheme is Derrymeen Battery Energy Storage System (100 MW battery storage, under construction since 1 May 2026), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BT71
Projects of 1 MW and more (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dungannon Energy Storage Systembattery storage | battery storage | 50 | under constructionupdated Mar 2020 | Jun 2018 | — | Mar 2020 | Mid Ulster | 1.9 |
| Derrymeen Battery Energy Storage Systembattery storage | battery storage | 100 | under constructionupdated Jun 2026 | Apr 2024 | granted Jun 2025 | Jun 2026 | Mid Ulster | 4.4 |
| Battery Energy Storage System in Newmillsbattery storage | battery storage | 24 | approved, not builtupdated Aug 2025 | Apr 2024 | granted Jul 2025 | Aug 2025 | Mid Ulster | 4.4 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Power Generation Development in Dungannonbattery storage | battery storage | — | application submitted may be out of dateupdated Sep 2025 | Sep 2022 | — | Sep 2025 | Mid Ulster | 1.4 |
| Solar PV Panels Installation in Dungannonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Dec 2024 | granted May 2025 | Jun 2025 | Mid Ulster | 3.1 |
| Solar Array Development in Dungannonsolar farm | solar farm | 0.3 | approved, not builtupdated Jan 2025 | May 2024 | granted Dec 2024 | Jan 2025 | Mid Ulster | 4.4 |
| Wind Turbine Development in Dungannonwind turbine | wind turbine | — | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Mid Ulster | 6.7 |
| Solar PV Array Development in Dungannonrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | Mid Ulster | 7.4 |
| Wind Turbine Development in Stewartstownwind turbine | wind turbine | 0.7 | approved, not builtupdated Mar 2024 | Feb 2023 | granted Feb 2024 | Mar 2024 | Mid Ulster | 8.0 |
| Wind Turbine Development in Stewartstownwind turbine | wind turbine | 0.1 | approved, not builtupdated Feb 2022 | Nov 2021 | granted Apr 2022 | Feb 2022 | Mid Ulster | 8.4 |
| Gortagammon Road Replacement Turbinewind turbine | wind turbine | 0.2 | approved, not builtupdated Jun 2024 | Feb 2021 | granted May 2024 | Jun 2024 | Mid Ulster | 8.8 |
| Legilly Roadwind turbine | wind turbine | 0.3 | approved, not built may be out of dateupdated Apr 2020 | Oct 2019 | granted Apr 2020 | Apr 2020 | Mid Ulster | 8.9 |
| Wind Turbine Development in Dungannonwind turbine | wind turbine | — | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Mid Ulster | 9.6 |
Distance from the average position of the BT71 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.3 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.4 |
| Wind turbine | 6 | 2 | 4 | 0 | 0 | 1.4 |
| Battery storage | 4 | 1 | 3 | 0 | 0 | 174 |
MW in pipeline: pending, approved and under-construction capacity.
How Mid Ulster decides solar, wind and battery applications
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT71, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.