Energy Projects Near You

Derrymeen Battery Energy Storage System (100 MW)

Derrymeen Battery Energy Storage System is a 100 MW battery storage project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2026; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
under constructionstatus in REPD
8 June 2026record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
19 April 2024Application submitted
30 June 2025Planning permission granted
1 May 2026Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
under construction
Record last updated
8 June 2026
Operator or applicant
SSE Renewables
Planning authority
Mid Ulster
Planning application reference
LA09/2024/0461/F
Address (REPD)
Lands Immediately NE of Tamnamore SubStn. and, C 150m SW of No 151 Ballynakilly
Council area (by location)
Mid Ulster
Time to decision
62 weeks
REPD reference
16444

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Battery Energy Storage System in Newmillsbattery storage24approved, not built<0.1
Dungannon Energy Storage Systembattery storage50under construction6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5039, -6.7704).