Energy Projects Near You

Dungannon Energy Storage System (50 MW)

Dungannon Energy Storage System is a 50 MW battery storage project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2019; the record was last updated on 3 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
under constructionstatus in REPD
3 March 2020record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
5 June 2018Application submitted
1 December 2019Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
under construction
Record last updated
3 March 2020
Operator or applicant
Low Carbon Storage Ireland
Planning authority
Mid Ulster
Planning application reference
LA09/2018/0803/F
Address (REPD)
77a Ballynakilly Road, Dungannon, Co Tyrone
Council area (by location)
Mid Ulster
REPD reference
7050

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Derrymeen Battery Energy Storage Systembattery storage100under construction6.2
Battery Energy Storage System in Newmillsbattery storage24approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5125, -6.6751).