Energy Projects Near You

Battery Energy Storage System in Newmills (24 MW)

Battery Energy Storage System in Newmills is a 24 MW battery storage project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 July 2025, not yet built; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
17 April 2024Application submitted
9 July 2025Planning permission granted
18 July 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
5 August 2025
Operator or applicant
Exergy Solutions Limited
Planning authority
Mid Ulster
Planning application reference
LA09/2024/0451/F
Address (REPD)
On Lands c 170m Se of No 17 Quintinmanus Road, Newmills
Council area (by location)
Mid Ulster
Time to decision
64 weeks
REPD reference
16456

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Derrymeen Battery Energy Storage Systembattery storage100under construction<0.1
Dungannon Energy Storage Systembattery storage50under construction6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5039, -6.7704).