Solar, wind and battery projects near Omagh (BT79)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT79 (Fermanagh and Omagh): 1 is waiting for a planning decision, 7 approved but not yet running. The largest live scheme is Doogary Road, Omagh (40 MW battery storage, approved on 13 December 2024, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BT79
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Unnamed wind turbine (REPD 4920)wind turbine | wind turbine | 2 | appeal withdrawnupdated Oct 2015 | Sep 2014 | — | Oct 2015 | Fermanagh and Omagh | 2.9 |
| 490m north East of no 64 Backglen Roadwind turbine | wind turbine | 2 | appeal withdrawnupdated Oct 2015 | Oct 2014 | — | Oct 2015 | Fermanagh and Omagh | 3.0 |
| Slieveard Wind Farmwind farm | wind farm | 17.5 | appeal withdrawnupdated Nov 2016 | Mar 2013 | refused Jul 2015 | Nov 2016 | Fermanagh and Omagh | 4.5 |
| Doogary Road, Omaghbattery storage | battery storage | 40 | approved, not builtupdated Jan 2025 | Mar 2023 | granted Dec 2024 | Jan 2025 | Fermanagh and Omagh | 7.6 |
| Baronywind farm | wind farm | 9.2 | refused on appealupdated Nov 2018 | Jun 2015 | refused May 2017 | Nov 2018 | Fermanagh and Omagh | 7.8 |
| Lisnaharney Road Wind Farmwind farm | wind farm | 42 | refused on appealupdated Jan 2017 | Apr 2013 | refused Jan 2017 | Jan 2017 | Fermanagh and Omagh | 8.5 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Craighill Roadwind turbine | wind turbine | 0.3 | approved, not built may be out of dateupdated Feb 2021 | Oct 2019 | granted Feb 2020 | Feb 2021 | Fermanagh and Omagh | 1.7 |
| Ballybrack Roadwind turbine | wind turbine | 0.2 | approved, not built may be out of dateupdated Jun 2019 | Dec 2018 | granted May 2019 | Jun 2019 | Fermanagh and Omagh | 5.7 |
| Mullanmore Roadwind turbine | wind turbine | 0.2 | application submitted may be out of dateupdated Feb 2022 | Dec 2020 | — | Feb 2022 | Fermanagh and Omagh | 8.3 |
| 20 Crannoge Roadwind turbine | wind turbine | — | approved, not builtupdated Jan 2024 | Jan 2023 | granted Jan 2024 | Jan 2024 | Fermanagh and Omagh | 8.7 |
| Replacement Wind Turbinewind turbine | wind turbine | 0.4 | approved, not builtupdated Jan 2022 | Jan 2021 | granted Dec 2021 | Jan 2022 | Fermanagh and Omagh | 9.1 |
| Aghnaglea Road (relplacement turbine)wind turbine | wind turbine | 0.2 | approved, not built may be out of dateupdated Dec 2019 | Jun 2019 | granted Oct 2019 | Dec 2019 | Fermanagh and Omagh | 9.2 |
| Camlough Roadwind farm | wind farm | 0.2 | approved, not builtupdated Jan 2021 | Dec 2020 | granted Apr 2022 | Jan 2021 | Fermanagh and Omagh | 9.4 |
Distance from the average position of the BT79 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 4 | 0 | 1 | 0 | 2 | 0.2 |
| Wind turbine | 8 | 1 | 5 | 0 | 0 | 1.4 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 40 |
MW in pipeline: pending, approved and under-construction capacity.
How Fermanagh and Omagh decides solar, wind and battery applications
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
All projects in Fermanagh and Omagh
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT79, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.