Slieveard Wind Farm (17.5 MW)

Slieveard Wind Farm is a 17.5 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 1 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
appeal withdrawnstatus in REPD
1 November 2016record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
26 March 2013Application submitted
16 July 2015Refused by the planning authority
19 November 2015Appeal lodged
4 October 2016Appeal withdrawn

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
appeal withdrawn
Record last updated
1 November 2016
Operator or applicant
Slieveard Wind Farm Ltd
Planning authority
Fermanagh and Omagh
Planning application reference
K/2013/0102/F
Appeal reference
2015/A0158
Turbines
7
Address (REPD)
Slieveard Mountain Glencordial and Rylagh townlands Omagh Co Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
120 weeks
REPD reference
4238

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lisnaharney Road Wind Farmwind farm42refused on appeal4.3
Doogary Road, Omaghbattery storage40approved, not built8.8
Bessy Bell 2 Extensionwind farm9permission expired9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6502, -7.2532).