Lisnaharney Road Wind Farm (42 MW)
Lisnaharney Road Wind Farm is a 42 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 20 January 2017; the record was last updated on 31 January 2017.
42 MWwind farm
refused on appealstatus in REPD
31 January 2017record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 April 2013 | Application submitted |
| 1 August 2014 | Appeal lodged |
| 20 January 2017 | Refused by the planning authority |
| 20 January 2017 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 42 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 31 January 2017
- Operator or applicant
- ARC NI 3 Ltd/Windyfields (Renewable Energy International)
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- K/2013/0181/F
- Appeal reference
- 2013/A0228
- Turbines
- 14
- Address (REPD)
- Lisnaharney, Omagh
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 197 weeks
- REPD reference
- 4207
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Slieveard Wind Farm | wind farm | 17.5 | appeal withdrawn | 4.3 |
| Bessy Bell 2 Extension | wind farm | 9 | permission expired | 7.6 |
| Rakelly | wind farm | 14 | refused | 8.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6875, -7.2727).