Barony (9.2 MW wind farm)

Barony is a 9.2 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 October 2018; the record was last updated on 27 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
refused on appealstatus in REPD
27 November 2018record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
26 June 2015Application submitted
19 May 2017Refused by the planning authority
13 June 2017Appeal lodged
10 October 2018Appeal refused

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
refused on appeal
Record last updated
27 November 2018
Operator or applicant
Island Renewable Energy
Planning authority
Fermanagh and Omagh
Planning application reference
LA10/2015/0283/F
Appeal reference
2017/A0050
Turbines
4
Turbine height
127 m
Address (REPD)
89 Barony Road and Northstone Quarry at Barong Road, Alddrumman, Townland, Drumnakilly, Mountfield, Omagh
Council area (by location)
Fermanagh and Omagh
Time to decision
99 weeks
REPD reference
6186

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land approx 75m South of 141wind farm20operational2.9
Cregganconroewind farm13.8operational8.8
Mullaghturk Mountainwind farm10.5refused9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6613, -7.0989).