Mullaghturk Mountain (10.5 MW wind farm)
Mullaghturk Mountain is a 10.5 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 October 2007; the record was last updated on 29 July 2010.
10.5 MWwind farm
refusedstatus in REPD
29 July 2010record last updated
Mid Ulstercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 23 December 2004 | Application submitted |
| 25 October 2007 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 10.5 MW
- Status (REPD)
- refused
- Record last updated
- 29 July 2010
- Operator or applicant
- Unknown
- Planning authority
- Mid Ulster
- Planning application reference
- H/2004/1395/F
- Turbines
- 7
- Address (REPD)
- Mullaghturk Mountain - Approximately 11km south west of Draperstown and 16km north west of Cookstown.
- Council area (by location)
- Mid Ulster
- Time to decision
- 148 weeks
- REPD reference
- 2958
Who decides
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Beltonanean Wind Farm | wind farm | 12 | appeal withdrawn | 5.1 |
| Cregganconroe | wind farm | 13.8 | operational | 5.7 |
| Battery Energy Storage System Facility Development in Pomeroy | battery storage | 48 | approved, not built | 7.5 |
| Land approx 75m South of 141 | wind farm | 20 | operational | 9.1 |
| Ballynagilly Renewable Energy Project | wind farm | 18.4 | appeal withdrawn | 9.5 |
| Barony | wind farm | 9.2 | refused on appeal | 9.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6709, -6.9498).