Energy Projects Near You

Mullaghturk Mountain (10.5 MW wind farm)

Mullaghturk Mountain is a 10.5 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 October 2007; the record was last updated on 29 July 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWwind farm
refusedstatus in REPD
29 July 2010record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
23 December 2004Application submitted
25 October 2007Refused by the planning authority

Project details

Technology
wind farm
Capacity
10.5 MW
Status (REPD)
refused
Record last updated
29 July 2010
Operator or applicant
Unknown
Planning authority
Mid Ulster
Planning application reference
H/2004/1395/F
Turbines
7
Address (REPD)
Mullaghturk Mountain - Approximately 11km south west of Draperstown and 16km north west of Cookstown.
Council area (by location)
Mid Ulster
Time to decision
148 weeks
REPD reference
2958

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beltonanean Wind Farmwind farm12appeal withdrawn5.1
Cregganconroewind farm13.8operational5.7
Battery Energy Storage System Facility Development in Pomeroybattery storage48approved, not built7.5
Land approx 75m South of 141wind farm20operational9.1
Ballynagilly Renewable Energy Projectwind farm18.4appeal withdrawn9.5
Baronywind farm9.2refused on appeal9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6709, -6.9498).