Land approx 75m South of 141 (20 MW wind farm)
Land approx 75m South of 141 is a 20 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2007; the record was last updated on 11 April 2011.
20 MWwind farm
operationalstatus in REPD
11 April 2011record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 3 February 2005 | Application submitted |
| 26 April 2005 | Planning permission granted |
| 1 July 2007 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 20 MW
- Status (REPD)
- operational
- Record last updated
- 11 April 2011
- Operator or applicant
- Private Developer
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- K/2005/0183/F
- Turbines
- 8
- Address (REPD)
- Land approx 75m South of 141 Greencastle Road, Omagh
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 12 weeks
- REPD reference
- 3251
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Barony | wind farm | 9.2 | refused on appeal | 2.9 |
| Mullaghturk Mountain | wind farm | 10.5 | refused | 9.1 |
| Cregganconroe | wind farm | 13.8 | operational | 10.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6863, -7.0886).