Energy Projects Near You

Solar, wind and battery projects near Omagh (BT78)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT78 (Fermanagh and Omagh): 7 are waiting for a planning decision, 5 approved but not yet running, 2 operational. The largest live scheme is Skreen Road (100 MW battery storage, application submitted on 20 December 2024, no decision recorded), 3.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
7awaiting a decision
5approved, not running
2operational

Projects within 10 km of BT78

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Skreen Roadbattery storagebattery storage100application submittedupdated Feb 2025Dec 2024—Feb 2025Fermanagh and Omagh3.8
Pollnalaght (Cornavarrow)wind farmwind farm38.4operationalupdated Nov 2018Jun 2006granted Oct 2009Nov 2018Fermanagh and Omagh4.2
Pigeon Topwind farmwind farm27under constructionupdated Mar 2020Sep 2011granted Nov 2012Mar 2020Fermanagh and Omagh5.1
Doogary Road, Omaghbattery storagebattery storage40approved, not builtupdated Jan 2025Mar 2023granted Dec 2024Jan 2025Fermanagh and Omagh6.3
Battery Energy Storage System Development in Drumquinbattery storagebattery storage87.8application submittedupdated Jan 2025Nov 2024—Jan 2025Fermanagh and Omagh7.5
Segully Road, Drumquinwind turbinewind turbine2approved, not builtupdated Dec 2023May 2023granted Dec 2023Dec 2023Fermanagh and Omagh7.5
Curraghamulkin (Dooish Wind Farm)wind farmwind farm30operationalupdated Oct 2018Mar 2008granted Nov 2017Oct 2018Fermanagh and Omagh8.9
Clunahill Wind Farmwind farmwind farm21approved, not built may be out of dateupdated Sep 2019Oct 2007granted Feb 2015Sep 2019Fermanagh and Omagh9.3
Townland of Tattymoyle Middle, Ecclesville Road Wind Farmwind farmwind farm72application submittedMay 2026——Fermanagh and Omagh9.3
Dunnaree Hill Wind Farmwind farmwind farm15application withdrawnupdated Mar 2015Apr 2011—Mar 2015Fermanagh and Omagh9.6
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Battery Energy Storage Development in Omaghbattery storagebattery storage—application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Fermanagh and Omagh3.5
Drumbarley Road, Drumquinwind farmwind farm—application submitted may be out of dateupdated May 2024Apr 2024—May 2024Fermanagh and Omagh3.6
Mullawinny Road (Replacement Turbine)wind turbinewind turbine0.2application withdrawnupdated Mar 2020Aug 2019—Mar 2020Fermanagh and Omagh4.4
Wind Turbine Development in Omaghwind turbinewind turbine—application submittedupdated May 2025Mar 2025—May 2025Fermanagh and Omagh5.1
Cavan Roadbattery storagebattery storage—approved, not builtupdated Aug 2025Sep 2024granted Jul 2025Aug 2025Fermanagh and Omagh5.2
Wind Turbine Development in Fintonawind turbinewind turbine—application submittedupdated Apr 2025Feb 2025—Apr 2025Fermanagh and Omagh9.1
Whitehill Roadwind turbinewind turbine0.2refusedupdated Dec 2021Apr 2021refused Dec 2021Dec 2021Derry City and Strabane9.6

Distance from the average position of the BT78 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm72220120
Wind turbine521012
Battery storage53200228

MW in pipeline: pending, approved and under-construction capacity.

How Fermanagh and Omagh decides solar, wind and battery applications

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

All projects in Fermanagh and Omagh

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT78, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.