Skreen Road (100 MW battery storage)
Skreen Road is a 100 MW battery storage project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 20 December 2024, no decision recorded; the record was last updated on 24 February 2025.
100 MWbattery storage
application submittedstatus in REPD
24 February 2025record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 December 2024 | Application submitted |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 100 MW
- Status (REPD)
- application submitted
- Record last updated
- 24 February 2025
- Operator or applicant
- Renewable Energy Systems Ltd
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- LA10/2025/0003/F
- Address (REPD)
- 320m SW of 22 Skreen Road
- Council area (by location)
- Fermanagh and Omagh
- Name in REPD
- Skreen Road - Battery Energy Storage System
- REPD reference
- 18111
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Pollnalaght (Cornavarrow) | wind farm | 38.4 | operational | 5.3 |
| Townland of Tattymoyle Middle, Ecclesville Road Wind Farm | wind farm | 72 | application submitted | 6.4 |
| Pigeon Top | wind farm | 27 | under construction | 7.2 |
| Doogary Road, Omagh | battery storage | 40 | approved, not built | 7.6 |
| Battery Energy Storage System Development in Drumquin | battery storage | 87.8 | application submitted | 8.5 |
| Crocknamona Wind Farm | wind farm | 17.5 | refused | 8.7 |
| Screggagh | wind farm | 19.5 | operational | 8.8 |
| Curraghamulkin (Dooish Wind Farm) | wind farm | 30 | operational | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5366, -7.3797).