Energy Projects Near You

Curraghamulkin (Dooish Wind Farm) (30 MW)

Curraghamulkin (Dooish Wind Farm) is a 30 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 July 2018; the record was last updated on 30 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
operationalstatus in REPD
30 October 2018record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
12 March 2008Application submitted
22 January 2016Appeal lodged
25 January 2016Refused by the planning authority
10 November 2017Planning permission granted
10 November 2017Appeal allowed
15 January 2018Construction started
15 July 2018Operational

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
operational
Record last updated
30 October 2018
Operator or applicant
DW Consultancy
Planning authority
Fermanagh and Omagh
Planning application reference
K/2008/0334/F
Appeal reference
2015/A0200
Turbines
10
Turbine height
130 m
Address (REPD)
Coolavannagh TD, Curraghmulkin TD, Dooish TD, Drumquin
Council area (by location)
Fermanagh and Omagh
Time to decision
504 weeks
REPD reference
4151

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Battery Energy Storage System Development in Drumquinbattery storage87.8application submitted1.5
Dunnaree Hill Wind Farmwind farm15application withdrawn2.1
Clunahill Wind Farmwind farm21approved, not built3.9
Pigeon Topwind farm27under construction4.3
Thornog Windfarmwind farm9.2operational4.3
Thornog Windfarm Extensionwind farm9.2operational4.3
Pollnalaght (Cornavarrow)wind farm38.4operational4.8
Slieveglasswind farm6.9operational7.3
Castlecraigwind farm25operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5778, -7.5141).