Slieveglass (6.9 MW wind farm)

Slieveglass is a 6.9 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 August 2018; the record was last updated on 27 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
27 November 2018record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
28 January 2008Application submitted
30 April 2012Refused by the planning authority
12 June 2013Planning permission granted
12 June 2013Appeal allowed
1 September 2017Construction started
10 August 2018Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
27 November 2018
Operator or applicant
Slieveglass wind farm (Energia)
Planning authority
Fermanagh and Omagh
Planning application reference
J/2008/0088
Appeal reference
2012/A0053
Turbines
3
Address (REPD)
Bullock Park, Drumquin, Co. Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
280 weeks
REPD reference
4065

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Castlecraigwind farm25operational1.3
Lough Hillwind farm10.5operational2.3
Bin Mountainwind farm9operational2.4
Thornog Windfarmwind farm9.2operational3.3
Thornog Windfarm Extensionwind farm9.2operational3.3
Binnawooda Wind Farmwind farm29.9application withdrawn3.9
Clunahill Wind Farmwind farm21approved, not built5.1
Dunnaree Hill Wind Farmwind farm15application withdrawn5.4
Aghamorewind farm15refused6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6355, -7.5692).