Bin Mountain (9 MW wind farm)

Bin Mountain is a 9 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2007; the record was last updated on 5 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
operationalstatus in REPD
5 January 2015record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
4 May 2001Application submitted
1 February 2006Planning permission granted
1 December 2006Construction started
1 February 2007Operational

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
5 January 2015
Operator or applicant
Greencoat UK Wind
Planning authority
Derry City and Strabane
Planning application reference
J/2004/0295/F
Turbines
6
Address (REPD)
Lough Hill Castle Craig, Curraghmacall Drummahon,
Council area (by location)
Derry City and Strabane
Time to decision
248 weeks
REPD reference
3113

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lough Hillwind farm10.5operational0.8
Castlecraigwind farm25operational1.6
Binnawooda Wind Farmwind farm29.9application withdrawn2.0
Slieveglasswind farm6.9operational2.4
Aghamorewind farm15refused4.3
Thornog Windfarm Extensionwind farm9.2operational4.9
Thornog Windfarmwind farm9.2operational4.9
Gronanwind farm9.2approved, not built5.3
Church Hillwind farm18.4operational7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6414, -7.6054).