Thornog Windfarm Extension (9.2 MW)

Thornog Windfarm Extension is a 9.2 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 December 2014; the record was last updated on 23 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
23 May 2016record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
1 April 2009Application submitted
11 September 2012Planning permission granted
13 June 2014Construction started
22 December 2014Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
23 May 2016
Operator or applicant
Energia Renewables
Planning authority
Fermanagh and Omagh
Planning application reference
K/2009/0243/F
Turbines
4
Address (REPD)
Thornog, Meenadoan townland, Drumquin. Co Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
180 weeks
REPD reference
4081

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thornog Windfarmwind farm9.2operational<0.1
Dunnaree Hill Wind Farmwind farm15application withdrawn2.9
Castlecraigwind farm25operational3.3
Slieveglasswind farm6.9operational3.3
Clunahill Wind Farmwind farm21approved, not built3.8
Lough Hillwind farm10.5operational4.3
Curraghamulkin (Dooish Wind Farm)wind farm30operational4.3
Bin Mountainwind farm9operational4.9
Binnawooda Wind Farmwind farm29.9application withdrawn5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6064, -7.5596).