Castlecraig (25 MW wind farm)

Castlecraig is a 25 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 August 2018; the record was last updated on 18 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWwind farm
operationalstatus in REPD
18 April 2019record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
15 December 2006Application submitted
1 June 2011Planning permission granted
20 April 2017Construction started
15 August 2018Operational

Project details

Technology
wind farm
Capacity
25 MW
Status (REPD)
operational
Record last updated
18 April 2019
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2006/1934/F
Turbines
10
Address (REPD)
Castlecraig (Slieve Glass) in Castlecraig, Sloughan, Killoan and Curraghmacall townlands. The proposed site is approximately 5 km south of Killen and 5 km west of Drumquin beside Lough Hill.
Council area (by location)
Derry City and Strabane
Time to decision
233 weeks
REPD reference
4112

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lough Hillwind farm10.5operational1.2
Slieveglasswind farm6.9operational1.3
Bin Mountainwind farm9operational1.6
Binnawooda Wind Farmwind farm29.9application withdrawn2.7
Thornog Windfarm Extensionwind farm9.2operational3.3
Thornog Windfarmwind farm9.2operational3.3
Aghamorewind farm15refused5.8
Dunnaree Hill Wind Farmwind farm15application withdrawn5.9
Clunahill Wind Farmwind farm21approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6309, -7.5872).