Church Hill (18.4 MW wind farm)

Church Hill is an 18.4 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2012; the record was last updated on 2 January 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
operationalstatus in REPD
2 January 2019record last updated
Derry City and Strabanecouncil area

Planning timeline

DateStage
6 April 2005Application submitted
26 April 2007Planning permission granted
1 May 2011Construction started
1 June 2012Operational

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
operational
Record last updated
2 January 2019
Operator or applicant
Greencoat (formerly Energia Renewables)
Planning authority
Derry City and Strabane
Planning application reference
J/2005/0358/F
Turbines
8
Address (REPD)
Church Hill, Meenamullan Road, Killeter, Castlederg, and Magherakeel, Killeter, Castlederg, Co Tyrone.
Council area (by location)
Derry City and Strabane
Time to decision
107 weeks
REPD reference
4047

Who decides

ApplicationsDerry City and StrabaneUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused0 of 212%
Onshore wind refused10 of 4345%
Battery storage refused0 of 416%
Median time from submission to decision103.3 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Meenamullen Wind Farmwind farm10refused1.2
BESS Facility Development in Killeterbattery storage82application withdrawn1.9
Aghamorewind farm15refused2.8
Gronanwind farm9.2approved, not built2.9
Crighshanewind farm32.2operational3.0
Crighshane Extensionwind farm15refused4.1
Meenablagh Wind Farmwind farm25refused on appeal5.7
Binnawooda Wind Farmwind farm29.9application withdrawn6.0
Bin Mountainwind farm9operational7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.654, -7.7128).