Meenamullen Wind Farm (10 MW)
Meenamullen Wind Farm is a 10 MW wind farm project in Derry City and Strabane, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 June 2019; the record was last updated on 28 June 2019.
10 MWwind farm
refusedstatus in REPD
28 June 2019record last updated
Derry City and Strabanecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 November 2013 | Application submitted |
| 11 June 2019 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- refused
- Record last updated
- 28 June 2019
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- Derry City and Strabane
- Planning application reference
- J/2013/0287/F
- Turbines
- 5
- Address (REPD)
- townland of Meenamullan near Killeter, Co Tyrone
- Council area (by location)
- Derry City and Strabane
- Time to decision
- 289 weeks
- REPD reference
- 4285
Who decides
| Applications | Derry City and Strabane | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 10 (20%) | 19% |
| Solar refused | 0 of 2 | 12% |
| Onshore wind refused | 10 of 43 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 103.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Church Hill | wind farm | 18.4 | operational | 1.2 |
| BESS Facility Development in Killeter | battery storage | 82 | application withdrawn | 1.7 |
| Crighshane | wind farm | 32.2 | operational | 2.4 |
| Aghamore | wind farm | 15 | refused | 3.2 |
| Gronan | wind farm | 9.2 | approved, not built | 3.9 |
| Crighshane Extension | wind farm | 15 | refused | 3.9 |
| Binnawooda Wind Farm | wind farm | 29.9 | application withdrawn | 5.8 |
| Meenablagh Wind Farm | wind farm | 25 | refused on appeal | 6.5 |
| Bin Mountain | wind farm | 9 | operational | 7.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6433, -7.7164).