Energy Projects Near You

Pigeon Top (27 MW wind farm)

Pigeon Top is a 27 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 17 December 2015; the record was last updated on 11 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
under constructionstatus in REPD
11 March 2020record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
26 September 2011Application submitted
15 November 2012Planning permission granted
17 December 2015Construction started

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
under construction
Record last updated
11 March 2020
Operator or applicant
Energia
Planning authority
Fermanagh and Omagh
Planning application reference
K/2011/0592/F
Turbines
9
Address (REPD)
Dooish, Drumquin, Omagh
Council area (by location)
Fermanagh and Omagh
Time to decision
59 weeks
REPD reference
4650

Earlier applications for this site

ApplicationMWSubmittedOutcome
Pigeon Top K/2009/008120.710 January 2009refused 12 January 2015

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pollnalaght (Cornavarrow)wind farm38.4operational2.2
Battery Energy Storage System Development in Drumquinbattery storage87.8application submitted2.9
Clunahill Wind Farmwind farm21approved, not built4.3
Curraghamulkin (Dooish Wind Farm)wind farm30operational4.3
Dunnaree Hill Wind Farmwind farm15application withdrawn4.6
Skreen Roadbattery storage100application submitted7.2
Thornog Windfarmwind farm9.2operational7.4
Thornog Windfarm Extensionwind farm9.2operational7.4
Slieveglasswind farm6.9operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5873, -7.4497).