Energy Projects Near You

Screggagh (19.5 MW wind farm)

Screggagh is a 19.5 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 March 2011; the record was last updated on 1 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.5 MWwind farm
operationalstatus in REPD
1 August 2016record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
18 April 2005Application submitted
13 May 2008Planning permission granted
1 July 2009Construction started
21 March 2011Operational

Project details

Technology
wind farm
Capacity
19.5 MW
Status (REPD)
operational
Record last updated
1 August 2016
Operator or applicant
Screggagh Windfarm
Planning authority
Fermanagh and Omagh
Planning application reference
K/2005/0810/F
Turbines
8
Address (REPD)
Screggagh, Screggagh & Stranisk townlands, Fintona. Co Tyrone
Council area (by location)
Fermanagh and Omagh
Time to decision
160 weeks
REPD reference
3263

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hunter's Hillwind farm20operational2.7
Townland of Tattymoyle Middle, Ecclesville Road Wind Farmwind farm72application submitted3.9
Glengesh Lower Forest (Murley)wind farm20.7operational5.5
Crocknamona Wind Farmwind farm17.5refused7.1
Skreen Roadbattery storage100application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4624, -7.3329).