Energy Projects Near You

Solar, wind and battery projects near Fivemiletown (BT75)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT75 (Mid Ulster): 1 approved but not yet running, 5 operational. The largest live scheme is Drumcor Road (1 MW wind turbine, approved on 8 July 2020, not yet built; REPD status may be out of date), 6.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
1approved, not running
5operational

Projects within 10 km of BT75

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glengesh Lower Forest (Murley)wind farmwind farm20.7operationalupdated Jun 2020Oct 2015granted May 2018Jun 2020Fermanagh and Omagh5.1
Drumcor Roadwind turbinewind turbine1approved, not built may be out of dateupdated Jul 2020Oct 2019granted Jul 2020Jul 2020Fermanagh and Omagh6.0
Slatbegwind farmwind farm20.7refusedupdated Apr 2012Dec 2006refused Feb 2009Apr 2012Mid Ulster6.7
Hunter's Hillwind farmwind farm20operationalupdated May 2016Feb 2005granted Dec 2008May 2016Fermanagh and Omagh7.4
Lendrum's Bridge Wind Farmwind farmwind farm5.9operationalupdated Feb 2010Sep 1997granted May 1998Feb 2010Mid Ulster8.9
Teigeswind farmwind farm11operationalupdated Nov 2018Mar 2008granted Dec 2014Nov 2018Fermanagh and Omagh9.4
Screggaghwind farmwind farm19.5operationalupdated Aug 2016Apr 2005granted May 2008Aug 2016Fermanagh and Omagh9.9

Distance from the average position of the BT75 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm600510
Wind turbine101001

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT75, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.