Energy Projects Near You

Slatbeg (20.7 MW wind farm)

Slatbeg is a 20.7 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 February 2009; the record was last updated on 5 April 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
refusedstatus in REPD
5 April 2012record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
15 December 2006Application submitted
9 February 2009Refused by the planning authority

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
refused
Record last updated
5 April 2012
Operator or applicant
DP Energy Ireland Ltd
Planning authority
Mid Ulster
Planning application reference
M/2006/1754/F
Turbines
9
Address (REPD)
Fardross Townland, (Slatbeg) Fardross Mountains, Clogher
Council area (by location)
Mid Ulster
Time to decision
112 weeks
REPD reference
2989

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lendrum's Bridge Wind Farmwind farm5.9operational2.9
Lendrum's Bridge Wind Farm ( Extension 2)wind farm7.3operational4.8
Slieve Beaghwind farm30application withdrawn9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3729, -7.2134).