Lendrum's Bridge Wind Farm (5.9 MW)
Lendrum's Bridge Wind Farm is a 5.9 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2000; the record was last updated on 23 February 2010.
5.9 MWwind farm
operationalstatus in REPD
23 February 2010record last updated
Mid Ulstercouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 September 1997 | Application submitted |
| 11 May 1998 | Planning permission granted |
| 1 February 2000 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 5.9 MW
- Status (REPD)
- operational
- Record last updated
- 23 February 2010
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- Mid Ulster
- Planning application reference
- not recorded
- Turbines
- 9
- Address (REPD)
- Lendrum's Bridge Murley Road, Fivemiletown County Tyrone
- Council area (by location)
- Mid Ulster
- Time to decision
- 34 weeks
- REPD reference
- 3568
Who decides
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Lendrum's Bridge Wind Farm ( Extension 2) | wind farm | 7.3 | operational | 2.2 |
| Slatbeg | wind farm | 20.7 | refused | 2.9 |
| Slieve Beagh | wind farm | 30 | application withdrawn | 6.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3927, -7.1834).