Energy Projects Near You

Lendrum's Bridge Wind Farm ( Extension 2) (7.3 MW)

Lendrum's Bridge Wind Farm ( Extension 2) is a 7.3 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 December 2002; the record was last updated on 6 January 2004.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWwind farm
operationalstatus in REPD
6 January 2004record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
12 September 1997Application submitted
11 May 1998Planning permission granted
20 December 2002Operational

Project details

Technology
wind farm
Capacity
7.3 MW
Status (REPD)
operational
Record last updated
6 January 2004
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Mid Ulster
Planning application reference
not recorded
Turbines
11
Address (REPD)
Lendrum's Bridge Murley RoadFivemiletown County Tyrone
Council area (by location)
Mid Ulster
Time to decision
34 weeks
REPD reference
3566

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lendrum's Bridge Wind Farmwind farm5.9operational2.2
Slatbegwind farm20.7refused4.8
Slieve Beaghwind farm30application withdrawn5.0
Shantavny Scotchwind farm16.1operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3938, -7.1489).