Teiges (11 MW wind farm)
Teiges is an 11 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 July 2018; the record was last updated on 27 November 2018.
11 MWwind farm
operationalstatus in REPD
27 November 2018record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 31 March 2008 | Application submitted |
| 12 December 2014 | Planning permission granted |
| 24 August 2017 | Construction started |
| 19 July 2018 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 11 MW
- Status (REPD)
- operational
- Record last updated
- 27 November 2018
- Operator or applicant
- Energia
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- L/2008/0459/F
- Turbines
- 5
- Address (REPD)
- Eshnanumera and Eshnasillog More townlands (adjacent to Lisnaskea Forest), Brookeborough TD, Co. Fermanagh
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 350 weeks
- REPD reference
- 4152
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3031, -7.3985).