Solar, wind and battery projects near Lisnaskea (BT92)
5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT92 (Fermanagh and Omagh): 3 approved but not yet running, 1 operational. The largest live scheme is Mulnahorn Road (0.2 MW wind turbine, approved on 17 December 2020, not yet built; REPD status may be out of date), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BT92
Projects of 1 MW and more (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Teigeswind farm | wind farm | 11 | operationalupdated Nov 2018 | Mar 2008 | granted Dec 2014 | Nov 2018 | Fermanagh and Omagh | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Nutfield Roadwind turbine | wind turbine | 0.3 | application withdrawnupdated Mar 2020 | Oct 2019 | — | Mar 2020 | Fermanagh and Omagh | 5.1 |
| Mulnahorn Roadwind turbine | wind turbine | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2020 | granted Dec 2020 | Dec 2022 | Fermanagh and Omagh | 7.5 |
| The Kids Road, Garrarooskywind turbine | wind turbine | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Jun 2020 | granted Oct 2021 | Oct 2021 | Fermanagh and Omagh | 8.1 |
| The Kids Road, Garrarooskywind turbine | wind turbine | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Aug 2021 | granted Oct 2021 | Oct 2021 | Fermanagh and Omagh | 8.1 |
Distance from the average position of the BT92 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 4 | 0 | 3 | 0 | 0 | 0.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Fermanagh and Omagh decides solar, wind and battery applications
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
All projects in Fermanagh and Omagh
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT92, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.