Energy Projects Near You

Solar, wind and battery projects near Belleek (BT93)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT93 (Fermanagh and Omagh): 2 approved but not yet running. The largest live scheme is Wind Turbine in Irvinestown (0.8 MW wind turbine, approved on 24 May 2024, not yet built), 8.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of BT93

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tullinoidwind farmwind farm6application withdrawnupdated Oct 2013Mar 2004—Oct 2013Fermanagh and Omagh6.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wind Turbine in Irvinestownwind turbinewind turbine0.8approved, not builtupdated Jun 2024Mar 2023granted May 2024Jun 2024Fermanagh and Omagh8.2
Shankill Roadwind turbinewind turbine0.3approved, not built may be out of dateupdated Feb 2021Jan 2020granted Oct 2020Feb 2021Fermanagh and Omagh8.5

Distance from the average position of the BT93 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100000
Wind turbine202001.1

MW in pipeline: pending, approved and under-construction capacity.

How Fermanagh and Omagh decides solar, wind and battery applications

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

All projects in Fermanagh and Omagh

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT93, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.