Crocknamona Wind Farm (17.5 MW)

Crocknamona Wind Farm is a 17.5 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 November 2014; the record was last updated on 5 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
refusedstatus in REPD
5 December 2014record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
20 December 2010Application submitted
13 November 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
refused
Record last updated
5 December 2014
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Fermanagh and Omagh
Planning application reference
K/2010/0758/F
Turbines
7
Address (REPD)
Killyfuddy Road, Glengeen, Trillick
Council area (by location)
Fermanagh and Omagh
Time to decision
203 weeks
REPD reference
4171

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Screggaghwind farm19.5operational7.1
Hunter's Hillwind farm20operational7.2
Glengesh Lower Forest (Murley)wind farm20.7operational8.2
Skreen Roadbattery storage100application submitted8.7
Townland of Tattymoyle Middle, Ecclesville Road Wind Farmwind farm72application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4668, -7.4417).