Energy Projects Near You

Solar, wind and battery projects near Maghera (BT46)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BT46 (Mid Ulster): 1 is waiting for a planning decision, 6 approved but not yet running, 1 operational. The largest live scheme is Corlacky Hill Wind Farm (36.3 MW wind farm, approved on 16 March 2021, not yet built; REPD status may be out of date), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
6approved, not running
1operational

Projects within 10 km of BT46

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Corlacky Hill Wind Farmwind farmwind farm36.3approved, not built may be out of dateupdated Apr 2021May 2016granted Mar 2021Apr 2021Mid Ulster5.3
Draperstown (Brackagh) Wind Farmwind farmwind farm6operationalupdated Apr 2017Feb 2009granted Jun 2010Apr 2017Mid Ulster6.6
Brockaghboy Wind Farm (Further Extension)wind farmwind farm10approved, not built may be out of dateupdated Sep 2020Oct 2019granted Aug 2020Sep 2020Mid Ulster8.1
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eden Roadwind turbinewind turbine0.3approved, not builtupdated May 2026Feb 2020granted Mar 2026May 2026Mid Ulster5.6
PV Panels Development in Tobermorerooftop solarrooftop solar—approved, not builtupdated Dec 2024Jun 2024granted Aug 2024Dec 2024Mid Ulster6.3
PV Panels Development in Tobermorerooftop solarrooftop solar—approved, not builtupdated Dec 2024Jun 2024granted Aug 2024Dec 2024Mid Ulster6.3
Drumard Road, Gulladuffsolar farmsolar farm—approved, not builtupdated Jun 2024Apr 2023granted Jun 2024Jun 2024Mid Ulster6.5
Turbine Development in Garvaghwind turbinewind turbine—application submittedupdated Mar 2025Jan 2025—Mar 2025Causeway Coast and Glens9.2

Distance from the average position of the BT46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000
Rooftop solar202000
Wind farm3021046.3
Wind turbine211000.3

MW in pipeline: pending, approved and under-construction capacity.

How Mid Ulster decides solar, wind and battery applications

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

All projects in Mid Ulster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BT46, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.