Draperstown (Brackagh) Wind Farm (6 MW)

Draperstown (Brackagh) Wind Farm is a 6 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 18 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
18 April 2017record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
9 February 2009Application submitted
28 June 2010Planning permission granted
26 May 2016Construction started
15 March 2017Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
18 April 2017
Operator or applicant
Renewable Energy Generation (REG)
Planning authority
Mid Ulster
Planning application reference
H/2009/0075/F
Turbines
3
Address (REPD)
Creagh Concrete Products Ltd, Brackagh Quarry, 29 Disert Road, Draperstown, Magherafelt
Council area (by location)
Mid Ulster
Time to decision
72 weeks
REPD reference
4361

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cullion wind farmwind farm25application submitted6.1
Crockandunwind farm15operational9.0
Corlacky Hill Wind Farmwind farm36.3approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8112, -6.7082).