Cullion wind farm (25 MW)
Cullion wind farm is a 25 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 19 July 2019, no decision recorded; the record was last updated on 27 September 2019. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
| Date | Stage |
|---|---|
| 19 July 2019 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 25 MW
- Status (REPD)
- application submitted
- Record last updated
- 27 September 2019
- Operator or applicant
- ABO Wind
- Planning authority
- Mid Ulster
- Planning application reference
- LA09/2019/0990/F
- Turbines
- 6
- Turbine height
- 145 m
- Address (REPD)
- 29 Cullion Road, Desertmartin, Magherafelt, Co Londonderry
- Council area (by location)
- Mid Ulster
- REPD reference
- 7530
Who decides
| Applications | Mid Ulster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 8 of 33 | 45% |
| Battery storage refused | 0 of 7 | 16% |
| Median time from submission to decision | 68.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Crockandun | wind farm | 15 | operational | 3.2 |
| Draperstown (Brackagh) Wind Farm | wind farm | 6 | operational | 6.1 |
| Ballynagilly Renewable Energy Project | wind farm | 18.4 | appeal withdrawn | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7588, -6.7357).