Energy Projects Near You

Doraville Wind Farm (119 MW)

Doraville Wind Farm is a 119 MW wind farm project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 October 2020; the record was last updated on 25 January 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

119 MWwind farm
refusedstatus in REPD
25 January 2021record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
6 July 2015Application submitted
26 October 2020Refused by the planning authority

Project details

Technology
wind farm
Capacity
119 MW
Status (REPD)
refused
Record last updated
25 January 2021
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Mid Ulster
Planning application reference
LA10/2015/0292/F
Turbines
33
Turbine height
140 m
Address (REPD)
Doraville, County Tyrone
Council area (by location)
Mid Ulster
Time to decision
277 weeks
REPD reference
4634

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Battery Energy Storage System Development in Moneymorebattery storage20approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.61, -6.6944).