Energy Projects Near You

Battery Energy Storage System Development in Moneymore (20 MW)

Battery Energy Storage System Development in Moneymore is a 20 MW battery storage project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 December 2025, not yet built; the record was last updated on 13 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtstatus in REPD
13 January 2026record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
18 December 2024Application submitted
11 December 2025Planning permission granted
16 December 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
13 January 2026
Operator or applicant
J D Excavations Tyrone Limited
Planning authority
Mid Ulster
Planning application reference
LA09/2024/1517/F
Address (REPD)
On Lands Approximately 140M SW of 9 Drumrot Road, Moneymore
Council area (by location)
Mid Ulster
Time to decision
51 weeks
REPD reference
18059

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Doraville Wind Farmwind farm119refused5.9
Ballynagilly Renewable Energy Projectwind farm18.4appeal withdrawn8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6626, -6.6866).