Energy Projects Near You

Whappstown & Castlegore Windfarms (23.1 MW)

Whappstown & Castlegore Windfarms is a 23.1 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 August 2019, not yet built; the record was last updated on 22 April 2020. REPD also records that the planning permission expired on 13 August 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23.1 MWwind farm
approved, not builtmay be out of datestatus in REPD
22 April 2020record last updated
Antrim and Newtownabbeycouncil area

REPD also records that the planning permission expired on 13 August 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
4 October 2018Application submitted
13 August 2019Planning permission granted
13 August 2024Permission expired

Project details

Technology
wind farm
Capacity
23.1 MW
Status (REPD)
approved, not built
Record last updated
22 April 2020
Operator or applicant
Capital Dynamics
Planning authority
Antrim and Newtownabbey
Planning application reference
LA02/2018/0897/F
Turbines
7
Turbine height
125 m
Address (REPD)
65 Whappstown Road, Moorfields, Ballymena,
Council area (by location)
Antrim and Newtownabbey
Time to decision
45 weeks
REPD reference
6790

Earlier applications for this site

ApplicationMWSubmittedOutcome
Whappstown Wind Farm G/2011/0052/F9.21 February 2011replaced by a revised application
Castlegore Wind Farm G/2011/0136/F23.18 April 2011replaced by a revised application

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kells Solar Farmsolar farm50application submitted1.7
Wolf Bog Wind Farmwind farm8.8operational2.6
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built2.7
Carncome, Lislunnan Roadbattery storage150approved, not built4.0
Corby Knowewind farm5operational4.1
Drumadarragh Wind Farmwind farm8refused on appeal4.8
Cloghinarneywind farm13.8refused on appeal5.3
Douglas Topwind farm51application withdrawn5.7
Elliot's Hill Wind Farmwind farm5operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8066, -6.1207).