Energy Projects Near You

Drumadarragh Wind Farm (8 MW)

Drumadarragh Wind Farm is an 8 MW wind farm project in Antrim and Newtownabbey, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 August 2014; the record was last updated on 19 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
refused on appealstatus in REPD
19 September 2014record last updated
Antrim and Newtownabbeycouncil area

Planning timeline

DateStage
19 May 2005Application submitted
15 November 2013Refused by the planning authority
18 August 2014Appeal refused

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
refused on appeal
Record last updated
19 September 2014
Operator or applicant
Drumdarragh Windfarm Ltd
Planning authority
Antrim and Newtownabbey
Planning application reference
U/2005/0281/F
Turbines
4
Address (REPD)
Drumadarragh Hill, Ballyclare, County Antrim
Council area (by location)
Antrim and Newtownabbey
Time to decision
443 weeks
REPD reference
4046

Who decides

ApplicationsAntrim and NewtownabbeyUK
Decided applications (solar, wind, battery)4010,236
Refused8 (20%)19%
Solar refused4 of 1412%
Onshore wind refused3 of 1945%
Battery storage refused1 of 716%
Median time from submission to decision48.1 weeks17.0 weeks
Appeals lodged / allowed7 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Antrim and Newtownabbey, South Antrim.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wolf Bog Wind Farmwind farm8.8operational3.1
Whappstown & Castlegore Windfarmswind farm23.1approved, not built4.8
Elliot's Hill Wind Farmwind farm5operational5.6
Kells Solar Farmsolar farm50application submitted6.4
Battery Energy Storage System Development in Ballymenabattery storage79approved, not built6.8
Corby Knowewind farm5operational7.4
Carncome, Lislunnan Roadbattery storage150approved, not built7.6
Douglas Topwind farm51application withdrawn8.1
Cloghinarneywind farm13.8refused on appeal8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7785, -6.0638).